They didn't do any work on Monday but they were out in force today. They started at the back already i can see a broken tile..
Facade
Florence
Tuesday, January 18, 2011
Thursday, January 13, 2011
Wednesday, January 12, 2011
Scaffold and Roof Tiles Delivered.
The scaffold for the roof has been installed and the Roof tiles delivered. I had a quick chat with our Site Supervisor and he has suggested that if all weather goes well we will be at Lock Up in 3 weeks!!!
Roof Tiles are Charcoal from Bristle Roof
thats a lot of roof tiles!!
Wednesday, January 5, 2011
Happy New Year 2011 to everyone.!!!
Well its back to the house progress. So far nothing this week, Wisdom is officially back on Monday 10th Jan..
Anyway, they actually squeezed in the guttering to our house last year... Sorry was a bit slack in taking photos, but I'll be out there tomorrow to take a better shot before the roofing starts next week.
Getting an inspection done before the internal lining starts. I intended to this so that the frames are still visible. I can already see some minor fixes required - dings on the window frames.. some dodgy work by the plumber (well his attempt at doing some carpentry).
I have so far paid 3 stages plus the deposit. so 2 more to go this year..
The list of things to do after the handover is now growing..
Thursday, December 23, 2010
As the year 2010 ends so does the construction progress.
There has been no further progress since the bricks were completed. Wisdom will now shut shop for 3 weeks starting today. It will be interesting to see what week they resume in January. My next post ofcourse will be then, so until then >>>> Have a Merry Festive Season and Happy New Year!!!!!!!!!!