13/12/2010 - Bricks is one day away from completion.
Facade
Florence
Monday, December 13, 2010
Tuesday, December 7, 2010
Another Clear Day of Bricklaying
Where the Gas Meter will go
Garage side almost complete
Leisure Room & Alfresco
Looks like i need to do some weed killing on the weekend.
Garage Wall - i suspect electric meter box to go in cutout
Monday, December 6, 2010
Bricklayers hard at work with the Weather playing the spoiler.
Bricks were delivered 26/11/2010 Then it rained for a WEEK
Whitsunday Orpheus
Monday 29/11/2010 they started then
the weather turned for the worse
What they got done in 1 and a bit day
Continuing on Friday 3/12/2010
The following are photos taken today 6/12/2010 which is now up to date with the postings.
Hope the good weather continues. More to come
Getting up to Date - Frames completed
Wednesday, November 10, 2010
FRAMES - In progess
They started yesterday after lunch and they continued today.. I expect 1 more day and they will be done with Roof frame/trussess installed. More to come tomorrow!!! Also didn't realise that they are terminte treated.. reason why the timber is coloured the way it is.